Water Connection


Procedure for Application

Step 1: Registration of the Applicant/Citizen in the website of e-District.

Step 2:Login in the e-District Portal and submit the PIN number as provided at the time of Building Plan Sanction.

Step 3:Submit the preferable data range for Connection for Water.

Step 4:Once process for physical connection has been done then digitally signed certificate for Water Connection will be generate and made available in dashboard of Applicant/Citizen.

Water charges (Non-Domestic)

Supply of water for non-domestic purpose, the rate shall be Rs. 20.00 per kilometre and the minimum rate of supply of water shall be as indicated below.

Minimum monthly charges for supply of water
Ferrule size Minimum monthly charges for supply of water (In rupees)
Up to 8 mm ₹ 200
Up to 8 Above 8 mm and up to 15 mm ₹ 750
Above 15 mm and up to 20 mm ₹ 1500
Above 20 mm and up to 32 mm ₹ 2500
Above 32 mm and for bulk connections ₹ 5000

Enlisted Plumbers under NKDA

Time line

Stipulated Time Limit for Rendering the Service

15 (Fifteen) Days
Office

New Town Kolkata Development Authority

Services

Water Connection

Designated Officer

CEO, NKDA

Appellate Officer

Joint Secretary

Reviewing Officer

Secretary / Principal Secretary

Contact Details

For more information Contact with NKDA

033-2324-2148 (Extension : 261 / 266)

ee2[at]nkda[dot]in